Clarifies definitions of Max Anticipated Surface Pressure for completion; how to handle a gas reservoir isolated by cement behind the production casing; describes when to use an oil gradient or gas gradient to calculate certain anticipated pressures prior to production.

Attachment
Document
NTL 2019-N04 (230.17 KB)
Document Type
Issued Date
Publication Date
Date for required review
NTL Status
Active
NTL Category
Drilling Operations (Subpart D)