Project Number | 146
|
---|---|
Program | |
Progress Date | 10/21/2016
|
Category | |
Project Initiation Date | 12/30/1991
|
Performing Activity | |
Principal Investigator | Mr. Robert G. Bea & Mr. Ben C. Gerwick
|
Contracting Agency | Minerals Management Service
|
Description | The objective of this project was to develop an engineering screening approach to assist in the development of inspection and repair methodologies for existing steel jacket platforms. Quantified safety assessments of inspections and repairs and the ability to incorporate these findings into decisions regarding future inspections and maintenance sequences was a major focus of this effort. |
Latest progress update | Complete. The research resulted in the development of a practicable methodology and guidelines for safety management of fixed offshore platforms. |
Status | Completed
|
Associated Attachments |